Engineering

Engineered, not assembled.

The membrane is shaped first and the steel is designed around it. Every structure is checked against the wind for its own site before anything is fabricated.

Close view of a tensioned architectural membraneIllustrative

The principle

A tensile roof weighs so little that the wind, not gravity, decides the design. Two numbers settle it: the design wind pressure for the site, and what the ground can hold.

From survey to handover

Seven steps, one calculation.

  1. Step 0101

    Survey and brief

    Dimensions, levels, access and the ground, plus what happens underneath: cars, people, forklifts, water or a crowd.

  2. Step 0202

    Design loads

    Site wind under IS 875 (Part 3), adjusted for terrain, height and importance. Our standard basis is 150 km/h, checked against the site's own figure.

  3. Step 0303

    Form-finding

    The membrane is shaped in 3D so it curves two ways at once. That curvature and pre-tension are what make fabric stiff.

  4. Step 0404

    Patterning

    The curved surface is cut into flat panels, each oriented to the warp and weft of the cloth, with compensation for stretch.

  5. Step 0505

    Fabrication

    Panels are joined by high-frequency welding. Steel is fabricated to the calculation and hot-dip galvanised.

  6. Step 0606

    Erection and tensioning

    Footings, steel, then the membrane is lifted and brought to its design pre-stress by our own crews.

  7. Step 0707

    Handover

    As-built drawings, mill certificates, a structural stability certificate and the O&M manual.

Form-finding

Curved two ways, so it stays tight.

A flat membrane can only sag. A saddle, curved up one way and down the other, carries downward load on one curvature and wind uplift on the other, stays taut and drains itself. Scroll to see the model tension.

Live model: hypar membranes, mast and cables

Load cases

What every structure is checked for.

  • 01Dead load

    Membrane, cables and steel. On a tensile roof this is small, which is exactly the problem.

  • 02Pre-stress

    The tension that holds the shape, pulling permanently on the frame and the footings.

  • 03Wind uplift

    The governing case. Pressure and suction for the site, not a generic figure.

  • 04Overturning

    A cantilever hangs the roof off one column line, so each footing resists a moment as well as a pull.

  • 05Soil above

    Earth over the footing helps hold it down, and is calculated, not assumed.

  • 06Rain and snow

    Downward cases are still checked, and in the hills snow can govern locally.

Design codes

What “engineered” means on paper.

  • IS 875 (Part 3)Design wind pressure for the site
  • IS 800Structural steel frame
  • IS 456Reinforced concrete footings
  • IS 4759 / IS 2629Hot-dip galvanising of the steelwork

Foundations

Sized for the pull, not the weight.

The same canopy needs a different footing in dense clay and in loose fill. A quotation that offers one footing size regardless of site has not looked at the site.

Isolated pad

Mass of the pad plus the soil bearing on it

The common case: one column, one footing, reasonable ground

Raft

One slab spreading load across a wider area

Weaker or variable soil, or columns close enough to share a base

Pile

Friction and end bearing down to firm strata

Soft or filled ground where a pad would be impractically large

Mass / anchor block

Sheer weight of concrete resisting a cable pull

Where stay cables come down to ground away from the frame

Ballast

Weight resting on the surface, no excavation

Demountable and temporary structures only

Handover and warranty

Two written warranties, both ours.

Not a manufacturer's pass-through. The membrane grade, and so where you sit in the five-to-fifteen-year band, is named in the quotation.

Structure and workmanship

One year

Steel, fabrication, installation and tensioning as built

Membrane

Five to fifteen years, by grade

Tear resistance, seam integrity and colour stability

Motorised and retractable systems

One year

Mechanism, drive and controls with the structure

  • As-built drawings

    What was actually built, not what was first proposed.

  • Mill certificates

    Traceability for the steel section and grade, years later.

  • Structural stability certificate

    Confirms the structure was designed and built to the calculation.

  • O&M manual

    The maintenance schedule the warranty assumes.

Maintenance

Kept tight, it lasts.

Loss of tension is behind most early failures. A slack membrane ponds water, flutters in wind and wears at the corners. This is a workable baseline for a permanent PVC or PVDF canopy in Indian conditions.

Compare membranes
  1. After every heavy stormWalk the site: ponding, torn edges, displaced fittings, blocked outlets.
  2. QuarterlyClear leaves, nests and silt from gutters, valleys and drains.
  3. Every 6–12 monthsWash the membrane; sooner on polluted, coastal or tree-shaded sites.
  4. AnnuallyFull technical inspection of seams, cables, fittings, tension, steel and coatings.
  5. Every 3–5 yearsDeep clean, make good steel coatings, review fastener torque.

Start a project

Need the calculation behind a quote?

Send the site location and the area to cover. We work out the wind for your site and show you the footing and steel it leads to.

or call +91 93159 45187